BS EN 12101-7: Smoke and heat control systems. Smoke duct sections
BS EN 12101-7 specifies requirements for smoke ducts used to convey smoke from extract points to discharge locations in mechanical smoke ventilation systems.
BS EN 12101-7 specifies the requirements for ducts used specifically in smoke ventilation systems - the ductwork that conveys smoke from extract grilles or damper positions to the point of discharge outside the building. Unlike standard HVAC ductwork, smoke ducts must maintain structural integrity and smoke-tightness under the elevated temperatures and pressures present during a fire event.
Part of the BS EN 12101 standard family.
Why Smoke Ducts Are Different
Standard ventilation ductwork is designed for ambient temperature operation. During a fire, smoke extract ductwork must:
- Withstand hot gas temperatures of 200°C or higher for extended periods
- Maintain a gas-tight seal so extracted smoke cannot leak into adjacent spaces
- Retain structural integrity under the mechanical stresses imposed by fire conditions
- Not contribute to fire spread through their fabric or insulation
BS EN 12101-7 establishes the test methods and performance classifications that allow smoke ducts to be selected and specified with confidence.
Key Requirements
Temperature and Duration Classification
Ducts are classified by the temperature they must withstand and the duration, using the same format as other BS EN 12101 components:
| Classification | Temperature | Duration |
|---|---|---|
| F200/30 | 200°C | 30 min |
| F200/60 | 200°C | 60 min |
| F200/120 | 200°C | 120 min |
| F300/60 | 300°C | 60 min |
| F600/30 | 600°C | 30 min |
For most UK residential and commercial buildings, F200/60 is the standard specification. High-rise or complex buildings may require F200/120.
Leakage Classification
Duct leakage is classified at test pressure conditions relevant to the system operating pressure. Tighter leakage classifications ensure extracted smoke cannot bypass the ductwork and enter occupied zones.
Structural Integrity
Ducts must not collapse, buckle, or open at joints under the combined effects of heat, negative pressure (extraction), and their own weight. Support spacings are specified to maintain alignment and prevent sagging.
Penetrations and Fire Stopping
Where smoke ducts pass through fire-rated walls or floors, the penetration must be appropriately fire-stopped. Any dampers installed in the duct must meet BS EN 12101-8 requirements.
Specification Checklist
When specifying smoke ducts under BS EN 12101-7, confirm:
- Temperature classification - e.g. F200/60
- Leakage class - tested leakage rate at system pressure
- Duct cross-section - rectangular or circular, in mm
- Material - steel gauge, insulation type and thickness
- Support centres - maximum spacing between hangers
- Joints and sealing - sealing method and classification
- CE marking and Declaration of Performance
Installation Requirements
- Install ducts level and to correct falls where drainage is required
- Support at specified centres - do not exceed maximum hanger spacing
- Seal all joints to the declared leakage class
- Fire-stop all penetrations through fire-rated elements
- Insulate where specified to maintain temperature performance
- Test ductwork for leakage before handover
Related Standards
- BS EN 12101-3 - Powered fans connected to smoke duct systems
- BS EN 12101-8 - Smoke dampers installed within ductwork
- BS EN 12101-10 - Power supply to fans and damper actuators
- Approved Document B & Building Safety Act - UK regulatory context